On a Saturday morning in February 2025, Katy Petrisin drove to work and couldn't turn into her own parking lot. She owns Ware Ware Studio in the Shops at Vintage Village on Durant Road in North Raleigh. As WRAL reported that weekend, the road outside had become "a sea of construction cones and heavy machinery." NCDOT had just started building a bridge to carry Durant Road over the CSX S-Line, the rail corridor planned for passenger service between Raleigh and Richmond.
Rogers Road in Wake Forest is next on that list. The same contractor, Blythe Construction of Charlotte, holds the contract, and The News & Observer reported on Oct. 29 that it can begin work as soon as Nov. 30. Durant Road is almost done, so it gives Rogers Road drivers the closest thing they have to a forecast.
What Durant Road Was Promised, and What It Got
When NCDOT awarded the Durant Road contract in July 2024, it said the bridge would be substantially finished by fall of 2026. In a December 2024 traffic notice, the agency moved that to spring 2027. By February 2026, crews had finished the roadway embankments leading up to the bridge, and NCDOT said building the bridge itself would begin that summer. Then in late October, Jason Orthner, head of NCDOT's Rail Division, told The News & Observer the span should be finished by Thanksgiving.
Finishing the span doesn't finish the job. On Nov. 6, NCDOT announced that a section of Leslieshire Drive would close starting Nov. 9 for about 120 days, weather permitting. Crews need that time to complete utility work and raise the old roadway so it meets the new Durant Road. Leslieshire stays open to local traffic only. Drivers can't reach Grassington Way from Leslieshire during the work, so residents use Keswick Woods Court to reach the detour, and through traffic uses Hawksmoor Drive to get to Durant Road. At 120 days, that closure runs into March 2027.
That's the pattern Rogers Road drivers can expect. The bridge is the visible milestone. Tying the neighborhood streets and driveways into a road that now sits higher comes after it, one side street at a time.
Rogers Road Starts Where Durant Started, With a Longer Runway
Lining up the two projects shows how much bigger the Wake Forest job is.
| Durant Road, Raleigh | Rogers Road, Wake Forest | |
|---|---|---|
| NCDOT project | P-5720 | P-5707 |
| Contractor | Blythe Construction | Blythe Construction |
| Construction dollars | $18.88 million winning bid, June 2024 | $40.085 million construction estimate |
| Visible work began | Traffic shift on Feb. 8, 2025 | Contractor can begin as soon as Nov. 30, 2026 |
| Expected finish | Span by Thanksgiving 2026 | Open to traffic by fall 2030 |
Durant went from its first traffic shift to a nearly finished bridge in under two years, which matches WRAL's "nearly two years" estimate when work began. NCDOT expects Rogers to take close to four. The cost is bigger too. NCDOT's project page estimates $54.735 million in total for Rogers Road: $14.650 million for right of way and utilities, plus $40.085 million for construction.
The start date has already moved. The Town of Wake Forest's project notice says late 2026 or early 2027. The Wake Forest Business & Industry Partnership expects the work to "begin in earnest by January 2027." The fall 2030 opening is a target, not a promise. Asked about a completion date, NCDOT spokeswoman Kim Deaner told the partnership, "You just don't know what's going to happen with the weather."
What Gets Built Where the Tracks Cross Today
Right now, Rogers Road narrows to two lanes to cross the tracks, and The News & Observer describes that crossing as a bottleneck. According to NCDOT's P-5707 project page, the finished project changes the area in these ways:
- A bridge in the same spot as the current crossing, with two 12-foot lanes each way, a 12-foot left-turn lane and 5½-foot sidewalks on both sides.
- Approaches with 5-foot sidewalks set back from traffic by 4-foot buffers.
- Heritage Branch Road moved so it meets Rogers Road at Capital Creek Drive, about 0.24 mile east of where it meets Rogers today.
- The Heritage Professional Park West entrance moved to a new intersection about 200 feet east, and the Wake Forest Heritage Business Park West driveway moved about 300 feet east.
- Retaining walls along the bridge approaches to limit the impact on neighboring properties, and a 96-inch culvert under Rogers Road replaced with a 108-inch pipe.
The rerouted intersections are where Durant's experience applies most directly. The bridge goes up in the middle, while the entrances and side roads around it have to be rebuilt to meet it.
There's one difference that should make daily driving easier. Durant Road stayed open with its lanes narrowed alongside the new construction. NCDOT plans to build a temporary road next to the Rogers Road work zone before anything else, and Deaner told the Business & Industry Partnership, "That gets done first." The project won't send drivers on a detour. She told The News & Observer that residents and businesses will keep access to their destinations throughout, with traffic moved onto temporary lanes at times.
A Bridge Built for Trains That Aren't Running Yet
This is the reason for the long timeline. According to The News & Observer, the S-Line currently carries a couple of slow CSX freight trains a day. At today's train traffic, the crossing could stay as it is. The bridge is for the trains the state is planning. NCDOT hopes to extend Amtrak's Piedmont service to Wake Forest by 2032, and in October the Federal Railroad Administration released $550 million for the S-Line, half of the federal money pledged in 2023.
Rogers Road is one of four bridges NCDOT is building to remove busy crossings along the line in Wake County. The others are at Durant, East Millbrook and New Hope Church roads in Raleigh. Work on New Hope Church Road started in February 2026 and is expected to take about three years. On the Wake Forest end, the town plans a downtown "mobility hub" that will serve as the S-Line rail station. Wake Forest Business & Industry Partnership president Jason Cannon calls the Rogers Road bridge "visible, tangible progress for the S-Line."
Durant and Rogers are also both tied to the next big road project. NCDOT's plan to turn Capital Boulevard into a limited-access expressway, known as U-5307, starts construction on its first two phases in 2031. Phase A runs from I-540 to Durant and Perry Creek roads. If the dates hold, the Rogers Road bridge opens about a year before that work begins.
The Corridor That Lives Alongside the Work
According to the Business & Industry Partnership, P-5707 affects Rogers Road from Forestville Road to just below South Main Street, a busy commercial stretch with businesses, medical offices and schools. Employers along the corridor include Summit Fire & Security and the Wireless Research Center, and families at Thales Academy use Rogers Road too.
Just off the corridor, Rogers Branch Road has filled in quickly this year. As Wake Forest Magazine reported on Oct. 1, Vira Bistro opened at 3604 Rogers Branch Road, serving breakfast and coffee from 8 a.m. to 1 p.m. and dinner from 5 to 10 p.m., Tuesday through Sunday. Pilates Addiction is in the same building. Blackbird Brewery and its cocktail lounge, Bird's Nest, are at 3608. Anstead's Cigar Barn opened across the road at 3605 in September, sharing a building with barre3 Wake Forest. Biscuit Belly has a building permit for 3601 Rogers Branch Road. Rogers Branch Road has already had its own lane closures this fall. Widening tied to the Wheat Field II shopping center cut it to one lane of two-way traffic between Forestville Road and Rogers Road from 9 a.m. to 4 p.m. daily, starting Sept. 21 and running through mid-October.
The Durant Road shops show how a business district gets through a project like this. When work began there, WRAL reported that the owners of Dog = Love were repainting discarded campaign signs into advertising, and the Neuse General Store was using social media to tell customers how to get into its parking lot. A store employee said the contractor had promised a flashing sign letting drivers know the businesses were open. She also said the first round of tree and brush clearing actually brought in more business. Over a four-year build, Rogers Road shops will be counting on the same kind of steady, everyday traffic from nearby residents.
Where Updates Will Come From
NCDOT calls its P-5707 PublicInput page the official source for construction status, traffic changes and schedule updates. You can sign up there for email or text alerts, and some notices will also go out on Nextdoor. For questions, the project email is [email protected], and the hotline is 984-205-6615, code 1830. The page also says NCDOT is working with Wake County Public Schools on anything that could affect school transportation and campus access.
When clients are deciding on timing or location along a corridor like Rogers Road, a construction schedule like this one is part of the conversation. If you want to talk about what the bridge work means for your corner of Wake Forest, Kendra Kohut would be glad to hear from you. Let's Connect.