About 50 feet above Black Creek, a weathered-steel bridge runs alongside Northwest Cary Parkway. It has a concrete deck and leaf-patterned panels with holes that let light through. The News & Observer reported that this makes it the highest pedestrian bridge in Cary. From the deck you can see the greenway below, and as of the Town of Cary's October 30 update, the whole trail is open again.
The Town's announcement says Black Creek Greenway "has fully reopened following the completion of approximately 2.5 miles of renovations." The trail now runs 7.1 miles without a break, from the Old Reedy Creek Trailhead at Lake Crabtree to the greenway hub at Bond Park. The rebuilt section is wider, but the bigger change is that it was designed to close less often.
A Trail Built Before Anyone Planned for This Much Use
The section between West Dynasty Drive and Old Reedy Creek Road was more than 25 years old when the renovation started. According to the Town's project page, the work was meant to bring it up to Cary's current greenway standard. The same page includes a photo of crews clearing the trail after a storm on January 3, 2022. Cleanup like that was part of owning a creekside trail laid out a generation ago.
The Town's list of objectives shows what it wanted to fix. Among them:
- Improve overall trail drainage
- Where possible, move sections of the trail away from flood-prone areas
- Realign the trail to remove sharp curves
- Upgrade and raise the existing bridges to reduce flooding
- Treat runoff when possible to improve water quality
- Remove the steep sidewalk connection on West Dynasty Drive
Most of that list deals with water and grade. The Town says the widening and realignment were meant to "improve safety, accommodate the increased use, and prevent storm damage." Cary describes Black Creek as one of its longest and most popular greenways, so every storm closure affected a lot of people.
What the Rebuild Actually Changed
The trail is now 12 feet wide, bridges included, which matches Cary's current design standard. Most of the work was below the pavement and along the creek. The first phase alone included five new pedestrian bridges, built on new foundations. Retaining walls and culverts went in before any of those bridges were set.
On the final stretch near Lake Crabtree, the project's August update described extra grading "adjacent to Lake Crabtree to meet flood pool requirements." In other words, the trail had to fit the lake's high-water design. That is a big reason the northern section took the work it did.
The project also included steps that were easy to miss from behind a detour sign. Before construction began on June 3, 2024, Town staff worked with the North Carolina Native Plant Society to move several plants out of the phase 1 work zone. In the end, the reopened trail runs through the same woods it always has.
Why It Opened Months Early
The full design-and-construction budget was $16.5 million, and about $12 million of it came from federal grants. Design and the flood study began in winter 2016. Construction was planned as a three-year job split into three phases, so only one section was closed at a time. Each phase included contractor incentives for early completion, and Crowder Construction Company was hired to do the work.
Those incentives show up in the dates:
| Phase | Section | Original window | What happened |
|---|---|---|---|
| 1 | West Dynasty Drive to North Cary Park | 2024–2025 | Dynasty-to-Livingstone segment reopened August 29, 2025 |
| 2 | North Cary Park to Weston Parkway | 2025–2026 | Reopened May 1, 2026, along with the Cary Parkway bridge |
| 3 | Weston Parkway to Old Reedy Creek Road Trailhead | 2026–2027 | Closed May 4, 2026; reported complete ahead of schedule in October 2026 |
Weather didn't help with the last phase. In August, the Town reported that heavy rain in July had slowed construction and was still expecting a winter reopening. By September, the target had moved to "this fall," with paving planned for mid-September. The trail was open by the end of October, about six months after phase 3 closed in early May, and a full season ahead of the original 2026–2027 timeline.
The Bridge That Fixed a Gap Above the Trail
The bridge from the opening paragraph was a separate project, timed to open with phase 2. It doesn't carry the greenway. It carries the sidewalk along Northwest Cary Parkway, across the ravine where the trail runs underneath.
Before May, the Cary Parkway road bridge had no shoulder or space for people on foot or on bikes, as the News & Observer put it. The new 285-foot pedestrian bridge fills a 650-foot gap in the sidewalk near North Cary Park.
Voters approved $4.8 million for it in the 2019 Shaping Cary's Tomorrow bond package. Later federal money, distributed through the Capital Area Metropolitan Planning Organization, covers nearly half of the bridge's total cost of about $9 million. Now that phase 3 is done, the sidewalk above and the greenway below are both open at the same time for the first time.
The North End Now Leads Somewhere
The last phase to reopen was the northern stretch, and it is also where Black Creek connects to the most trails outside Cary. Here are the stops from north to south:
- Old Reedy Creek Trailhead. This is the northern end of Black Creek. It has parking for 82 cars, a restroom, water and a bike repair station. East of the trailhead, the route to Reedy Creek Greenway through Umstead State Park follows 0.6 miles of Old Reedy Creek Road. Past the I-40 bridge, that road is gravel.
- Crabtree Creek Greenway branch. About half a mile south of the northern end, a lakeside branch splits off from Black Creek and runs to Morrisville's trail west of Evans Road. Together they make a continuous 4.5-mile route from Black Creek to Davis Drive.
- Lake Crabtree County Park. The Town lists the county park among the greenway's direct connections.
- North Cary Park and the Cary Parkway bridge. This is where the phase 2 work and the new sidewalk bridge meet.
- Godbold Park. The trail connects to Godbold Park, the Cary Dog Park at Godbold and Cary Action Sports at Godbold.
- Fred G. Bond Metro Park. At the southern hub, Black Creek connects to the Bond Lake Trail, the Pine Cone and Paw Paw trails, the Bond Park Boat House and White Oak Creek Greenway. White Oak is 4.8 miles of trail sections, and the Town plans for it to eventually connect to the American Tobacco Trail.
The Black Creek and White Oak trails in Cary are part of the East Coast Greenway, which is planned to eventually run from Maine to Florida. On the Cary section of that route, the rebuilt north end is the link that reaches Umstead and Morrisville.
Before You Head Out
The greenway is open dawn to dusk. After the clocks fall back, that leaves noticeably less time for an after-work loop. It's open for walking, running, biking, leashed dogs, strollers and wheelchairs. The Town notes that some parts of the trail may be too steep for wheelchair use. Restrooms are at North Cary Park, Godbold Park, Fred G. Bond Metro Park and the Old Reedy Creek Road Trailhead.
If you skipped the north end while it was closed for the past six months, a good first trip back is to start at the Old Reedy Creek Trailhead and walk south toward Weston Parkway. That newest stretch passes the Lake Crabtree grading and ends at the trail section that reopened in May.
When I talk with clients about Cary, I end up talking about Black Creek, the dog park at Godbold and the new bridge at North Cary Park as much as about the houses. If you'd like to talk through which parts of Cary sit closest to the trail, Kendra Kohut would love to hear from you. Let's Connect.